Jal Nigam — Old Schemes Executive Summary
Whoodhill Infrastructure
LTD
Total Assign District
Assign Districts
Total Schemes / RVs
DPRs to be Prepared (Schemes / RVs)
DPRs Prepared till date (Schemes / RVs)
Pending DPRs (Schemes / RVs)
PPRBD Approved(Schemes / RVs)
O&M EMB Details
Total Bill Details
Total Generated Bill
325
Total Generated Bill Amt(Lakh)
132.26
Pending Bill
25
Pending Bill Amt(Lakh)
15.67
Paid Bill
300
Paid Bill Amt(Lakh)
132.26
Category A Bill Details
Total Generated Bill
0
Total Generated Bill Amt(Lakh)
0.00
Pending Bill
0
Pending Bill Amt(Lakh)
0.00
Paid Bill
0
Paid Bill Amt(Lakh)
0.00
Category B Bill Details
Total Generated Bill
325
Total Generated Bill Amt(Lakh)
132.26
Pending Bill
25
Pending Bill Amt(Lakh)
15.67
Paid Bill
300
Paid Bill Amt(Lakh)
132.26
Category C Bill Details
Total Generated Bill
0
Total Generated Bill Amt(Lakh)
0.00
Pending Bill
0
Pending Bill Amt(Lakh)
0.00
Paid Bill
0
Paid Bill Amt(Lakh)
0.00
Costing
Average Costing of all DPRs prepared till now (Without Solar & SCADA)(Lakh)
245.63
Average Costing of all DPRs prepared till now (With Solar & SCADA)(Lakh)
332.26
Category wise Details
Category A
Total Schemes / RVs
DPRs Prepared (Schemes / RVs)
PPRBD Approved(Schemes / RVs)
Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
0.00
Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
0.00
Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
0.00
Category B
Total Schemes / RVs
DPRs Prepared (Schemes / RVs)
PPRBD Approved(Schemes / RVs)
Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
188.87
Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
245.63
Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
332.26
Category C
Total Schemes / RVs
DPRs Prepared (Schemes / RVs)
PPRBD Approved(Schemes / RVs)
Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
0.00
Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
0.00
Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
0.00
Agreements
Details of Agreements Signed for O&M
Total Schemes / RVs
Agreements Signed till date (Schemes / RVs)
Pending for Agreement signing (Schemes / RVs)
Category A
Total(Schemes / RVs)
Signed(Schemes / RVs)
Pending(Schemes / RVs)
Category A
Total(Schemes / RVs)
Signed(Schemes / RVs)
Pending(Schemes / RVs)
Category A
Total(Schemes / RVs)
Signed(Schemes / RVs)
Pending(Schemes / RVs)
Category Wise DPR Value
Fully Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|
Partialy Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|---|---|---|---|---|
| Total | 25 | 29 | 6140.66 | 245.63 | 211.75 |
| 100 to 150 Lakh | 7 | 8 | 968.00 | 138.29 | 121.00 |
| 150 to 200 Lakh | 4 | 4 | 679.56 | 169.89 | 169.89 |
| Above 200 Lakh | 14 | 17 | 4493.10 | 320.94 | 264.30 |
Non- Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|
All DPR Range
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|---|---|---|---|---|
| Total | 25 | 29 | 6140.66 | 245.63 | 211.75 |
| 100 to 150 Lakh | 7 | 8 | 968.00 | 138.29 | 121.00 |
| 150 to 200 Lakh | 4 | 4 | 679.56 | 169.89 | 169.89 |
| Above 200 Lakh | 14 | 17 | 4493.10 | 320.94 | 264.30 |
Fully Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|
Partialy Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|---|---|---|---|---|
| Total | 25 | 29 | 6140.66 | 245.63 | 211.75 |
| Above 100 Lakh | 25 | 29 | 6140.66 | 245.63 | 211.75 |
Non- Functional
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|
All DPR Range
| Range | No's OF Schemes | No of Rv's | Total Work Cost | Average Work Cost (Scheme wise)(Lakh) | Average Work Cost (Village wise)(Lakh) |
|---|---|---|---|---|---|
| Total | 25 | 29 | 6140.66 | 245.63 | 211.75 |
| Above 100 Lakh | 25 | 29 | 6140.66 | 245.63 | 211.75 |