Brief Description of Works
District
Bijnor
Scheme ID
4594569
Scheme Name
Rehar W/s Scheme
Village Covered
1
Original Scheme Year
2007
Amount (Lakh)
97.71
Retrofitting Year
0
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
1
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
1
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
1214
Pipe Line (Replacement)
1649
FHTC Existing
889
FHTC Repair
254
FHTC New
166
Status
Specific reason for increasing cost
1.5. Since schemes are more then 10 years old and the water level is getting decreased in the tubewells , it has been observed that the condition of the tubewells is deteriorating day by day. Considering this situation, necessasry provisions have been made for the repair of existing tubewells, and in some locations, new tubewells have also been proposed.
2.2. Most of the schemes in district bijnor are more then 10 years old and In the earlier Gram Panchayat (GP) area, PVC pipes were used with a specified diameter. However, due to the recent extension of the GP area, additional piping is now required and as per the latest guidelines HDPE pipes are being used for extensions which is resulting in a rise in overall project cost. Moreover, to maintain the minimum required pressure at the tail e