Brief Description of Works

District Bijnor
Scheme ID 4595979
Scheme Name Harewala Village Water Supply scheme
Village Covered 1
Original Scheme Year 2014
Amount (Lakh) 188.47
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 1
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. 1
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 892
Pipe Line (Replacement) 1623
FHTC Existing 364
FHTC Repair 104
FHTC New 124
Status
Specific reason for increasing cost 1.5. Since schemes are more then 10 years old and the water level is getting decreased in the tubewells , it has been observed that the condition of the tubewells is deteriorating day by day. Considering this situation, necessasry provisions have been made for the repair of existing tubewells, and in some locations, new tubewells have also been proposed. 2.1. The base year for the scheme has been updated to 2025. As a result, population forecasting is showing higher values, leading to an increase in projected demand. Consequently, the diameter of the distribution pipeline is being increased to meet the revised demand, which is resulting in a rise in overall project cost.