Brief Description of Works

District Moradabad
Scheme ID 4604805
Scheme Name Bilakudan W/s Scheme
Village Covered 2
Original Scheme Year 2019
Amount (Lakh) 256.00
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 1284
Pipe Line (Replacement) 1137
FHTC Existing 891
FHTC Repair 680
FHTC New 278
Status Partially Functional > 70 lacs
Specific reason for increasing cost Two villages are included under the scheme. Since the base year is 2025, the population has increased and with this increase in population, the demand for water has also increased. Due to the increase in water demand, the size of the pipeline has increased and hence some pipeline and drinking water house connections have been proposed.