Brief Description of Works

District Moradabad
Scheme ID 4605005
Scheme Name Barbara Mazra water supply scheme
Village Covered 1
Original Scheme Year 2013
Amount (Lakh) 517.48
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 4062
Pipe Line (Replacement) 1970
FHTC Existing 1032
FHTC Repair 460
FHTC New 367
Status Partially Functional > 70 lacs
Specific reason for increasing cost Under the scheme, pipelines have not been laid in one hamlet. Due to population growth, pipelines have been extended, and pipelines are damaged at various locations. Consequently, new pipelines and the addition of some drinking water houses have been proposed.