Brief Description of Works
District
Moradabad
Scheme ID
4605015
Scheme Name
Moudha SAGY PWS Scheme
Village Covered
2
Original Scheme Year
2018
Amount (Lakh)
315.79
Retrofitting Year
0
Amount (Lakh)
0.00
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
1891
Pipe Line (Replacement)
2557
FHTC Existing
409
FHTC Repair
234
FHTC New
109
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
Two villages are included under the scheme. Due to the increase in population, the pipeline has been extended under this scheme. The pipeline is damaged and blocked at various locations, due to which it is proposed to install new pipelines and connect some drinking water houses.
