Brief Description of Works

District Moradabad
Scheme ID 4605015
Scheme Name Moudha SAGY PWS Scheme
Village Covered 2
Original Scheme Year 2018
Amount (Lakh) 315.79
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 1891
Pipe Line (Replacement) 2557
FHTC Existing 409
FHTC Repair 234
FHTC New 109
Status Partially Functional > 70 lacs
Specific reason for increasing cost Two villages are included under the scheme. Due to the increase in population, the pipeline has been extended under this scheme. The pipeline is damaged and blocked at various locations, due to which it is proposed to install new pipelines and connect some drinking water houses.