District Moradabad
Scheme ID 460923
Scheme Name Imratpur Fakhruddin W/s Scheme
Village Covered 1
Original Scheme Year 2017
Amount (Lakh) 148.19
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Repairing Work of boundary Wall, Approach Road, Water Recharge & Campus Development Work
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 786
Pipe Line (Replacement) 97
FHTC Existing 390
FHTC Repair 160
FHTC New 144
Status Fully Functional > 20 lacs
Specific reason for increasing cost Pipe line work extended due to population growth & damaged pipelines at various locations, new pipelines and the addition of FHTC have been proposed under the scheme.