Brief Description of Works

District Budaun
Scheme ID 4753509
Scheme Name KHEDA JALALPUR PUKHTA
Village Covered 1
Original Scheme Year 2015
Amount (Lakh) 797.91
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 2
Boundary Wall and Campus Devp. Yes
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 7000
Pipe Line (Replacement) 13000
FHTC Existing 1540
FHTC Repair 1060
FHTC New 1754
Status Partially Functional > 70 lacs
Specific reason for increasing cost Scheme covers 19 majras, all of them are scattered in approx 22 km radius. In this scheme 61.70 km pipeline was laid previously out of which 13 km pipeline is damaged, which needs to be replaced and 7 km pipeline extension is required. 1754 new FHTCs and 1060 FHTCs are proposed for repairing.