Brief Description of Works
District
Bareilly
Scheme ID
4766902
Scheme Name
Tisua water supply scheme
Village Covered
1
Original Scheme Year
2015
Amount (Lakh)
274.08
Retrofitting Year
2020
Amount (Lakh)
97.35
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
0
Boundary Wall and Campus Devp.
40 m boundary wall
Pump House (New)
0
Pump House (Repair)
0
Pipe Line (New)
0
Pipe Line (Replacement)
2
FHTC Existing
1410
FHTC Repair
365
FHTC New
221
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
5.982 km pipe line needs to relaced and newly laid. One habitation is on the other side of NH. So crossing of NH is also part of DPR. Boundary wall is also damagedin zone -2 of scheme. 365 connections need to be repaired and 221 no of new connections are also required.
