Brief Description of Works

District Unnao
Scheme ID 4827484
Scheme Name Baksar water Supply scheme
Village Covered 2
Original Scheme Year 2009
Amount (Lakh) 128.00
Retrofitting Year 2020
Amount (Lakh) 73.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. 11.35 lac (Construction of Baun drywall 30 m, Plaster & painting, supply and fixing of gate)
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 8206
Pipe Line (Replacement) 10562
FHTC Existing 223
FHTC Repair 199
FHTC New 448
Status Non-Functional > 100 lacs
Specific reason for increasing cost 1. Total existing pipeline of scheme is 3.9 km (4 kg PVC pipe) with respect to the requirement of 22.71 km as per present survey of OMIL to make the scheme fully functional. 2. Road dismantling & restoration of the 10.00 km required for pipe laying & new HSC. 3. Total existing FHTC found at site 223 with respect to the required 671 House hold as per the present OMIL survey out of 223 FHTC, 199 FHTC are damaged condition need to repair. also, no of 448 new HSC is required to the fully functional. 4.2011 census population 3208 at present for year 2025 is 3835.