Brief Description of Works
District
Unnao
Scheme ID
4827509
Scheme Name
SAHRAWAN WSS
Village Covered
2
Original Scheme Year
2008
Amount (Lakh)
165.40
Retrofitting Year
2020
Amount (Lakh)
170.69
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
1
Boundary Wall and Campus Devp.
Dismantling of existing Plaster & new plaster work, painting
Pump House (New)
0
Pump House (Repair)
1
Pipe Line (New)
24362
Pipe Line (Replacement)
0
FHTC Existing
678
FHTC Repair
248
FHTC New
290
Status
Non-Functional > 100 lacs
Specific reason for increasing cost
1. Total existing pipeline of scheme is 6.41 km with respect to the requirement of 30.77 km as per present survey of OMIL to make the scheme fully functional.
2. Road dismantling & restoration of the 10.26 km required for pipe laying & new HSC.
3. Total existing FHTC found at site 678 with respect to the required 968 Household as per the present OMIL survey out of 968 FHTC, 248 FHTC are damaged condition need to repair. also, no of 90 new HSC is required to the fully functional. And two no Tubewell