Brief Description of Works

District Unnao
Scheme ID 4827786
Scheme Name Behta mujawar water supply scheme
Village Covered 2
Original Scheme Year 2013
Amount (Lakh) 169.00
Retrofitting Year 2020
Amount (Lakh) 76.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Dismantling of existing Plaster & new plaster work, painting, etc.
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 2372
Pipe Line (Replacement) 1325
FHTC Existing 286
FHTC Repair 63
FHTC New 586
Status Non-Functional > 100 lacs
Specific reason for increasing cost 1. Total existing pipeline of scheme is 17.38 km with respect to the requirement of 21.08 km as per present survey of OMIL to make the scheme fully functional. 2. Road dismantling & restoration of the 3.23 km required for pipe laying & new HSC. 3. Total existing FHTC found at site 286 with respect to the required 872 Household as per the present OMIL survey out of 286 FHTC, 63 FHTC are damaged condition need to repair. also, no of 586 new HSC is required to the fully functional.