Brief Description of Works

District Unnao
Scheme ID 4827796
Scheme Name Bihar water supply scheme (Zone-1 Bihar, Zone-2 Ra
Village Covered 1
Original Scheme Year 2014
Amount (Lakh) 349.00
Retrofitting Year 0
Amount (Lakh) 0.00
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 2
Boundary Wall and Campus Devp. Dismantling of existing Plaster & new plaster work, painting
Pump House (New) 0
Pump House (Repair) 2
Pipe Line (New) 15785
Pipe Line (Replacement) 0
FHTC Existing 485
FHTC Repair 284
FHTC New 547
Status Non-Functional > 100 lacs
Specific reason for increasing cost 1. Total existing pipeline of scheme is 16.2 km with respect to the requirement of 31.98 km as per present survey of OMIL to make the scheme fully functional. 2. Road dismantling & restoration of the 3.29 km required for pipe laying & new HSC. 3. Total existing FHTC found at site 485 with respect to the required 1032 Household as per the present OMIL survey out of 1032 FHTC, 284 FHTC are damaged condition need to repair. also, no of 547 new HSC is required to the fully functional. 4. One no NHAI crossing (cost is lac), two no FRU, two OHT Zone