Brief Description of Works

District Kannauj
Scheme ID 4866008
Scheme Name Tilsara
Village Covered 1
Original Scheme Year 0
Amount (Lakh) 187.32
Retrofitting Year 0
Amount (Lakh) 44.49
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 0
Boundary Wall and Campus Devp.
Pump House (New) 0
Pump House (Repair) 0
Pipe Line (New) 0
Pipe Line (Replacement) 0
FHTC Existing 0
FHTC Repair 0
FHTC New 0
Status Non-Functional > 100 lacs
Specific reason for increasing cost THE SCHEME WAS CONSTRUCTED IN 2013-14 & COVER 1 REVENUE VILLAGES & 4 HABITATIONS. 9428 MTR OLD HDPE PIPELINE FOUND DAMAGE DURING ROAD EXTENSION & DRAIN CONTRUCTION WORK BY PRADHAN. 4629 MTR OLD PIPE LINE REPLACE WITH NEW HDPE PIPE, 94 NEW FHTC WHICH WAS NOT PROVIDED PREVIOUSLY & 269 FHTC CONNECTION GI PIPE MISSING, REPAIRING, GROUTING & NEW GI PIPE REQUIRED VALVES NOT AVAILBLE, SO SLUICE VALVES AND AIR VALVES HAVE BEEN CONSIDERED. OHT TANK WATERPROOFING, PAINTING, MS LADDER REPLACEMENT & RAILING REPAIRING, MS CAGE REQUIRED. SOME REPAIR WORK IS ALSO REQUIRED FOR THE BOUNDARY WALL ,STAFF QUARTER & PUMP HOUSE.