Brief Description of Works

District Kannauj
Scheme ID 4866578
Scheme Name Paraspur Saraiya Water Supply Scheme
Village Covered 1
Original Scheme Year 0
Amount (Lakh) 78.76
Retrofitting Year 0
Amount (Lakh) 52.49
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 0
Boundary Wall and Campus Devp.
Pump House (New) 0
Pump House (Repair) 0
Pipe Line (New) 0
Pipe Line (Replacement) 0
FHTC Existing 0
FHTC Repair 0
FHTC New 0
Status Partially Functional > 70 lacs
Specific reason for increasing cost THIS SCHEME IS CONSTRUCTED IN 2012 COVERED 4 HABITATION. THIS SCHEME IS CONSIDERED AS A PARTIALLY FUNCTIONAL SCHEME IN THIS SCHEME 4 KG PVC WERE USED IN DISTRIBUTION NETWORK HAVING LENGTH 8277 METER. AS NETWORK ARE DAMAGED, WE ARE CONSIDERING ONLY 6164 MTR WE WILL ONLY REPAIR LEAKS, CARRY OUT JOINT, REPLACE/EXTEND PIPES. 1317 METER OF NEW LINE HAVE BEEN PROPOSED TO START REGULAR WATER SUPPLY TO EVERY HOUSE HOLD & 60 NEW FHTC ARE ALSO PROPOSED FOR NEWLY CONSTRUCTED HOUSE HOLD & 222 REPAIRING FHTC. THE OLD TUBE WELL ARE TOTALLY DAMAGED SO, WE PROPOSED NEW TUBE WELL. CONDITION OF OHT IS ALSO VERY BAD MANY SEEPAGE ARE FOUND IN THE OHT SO WE CONSIDERED WATER PROOFING & PAINTING WORK AS WELL. BOUNDARY WALL IS CRACKED & BROKEN NEED MAJOR REPAIR WORK. ROAD RESTORATION IS ALSO NEEDED.