Brief Description of Works

District Kannauj
Scheme ID 4866582
Scheme Name ANAUGI WATER SUPPLY SCHEME
Village Covered 1
Original Scheme Year 0
Amount (Lakh) 188.91
Retrofitting Year 0
Amount (Lakh) 185.97
New T/W 3
Rebore T/W 0
New OHT 0
Repair OHT 0
Boundary Wall and Campus Devp.
Pump House (New) 0
Pump House (Repair) 0
Pipe Line (New) 0
Pipe Line (Replacement) 0
FHTC Existing 0
FHTC Repair 0
FHTC New 0
Status Non-Functional > 100 lacs
Specific reason for increasing cost THE SCHEME COVERS 14 HABITATION. REGULAR WATER SUPPLY IS RUNNING ONLY IN 8 HABITATION . DURING CONSTRUCTION, A 4 KG PVC WAS USED. AS PER OUR SURVEY, THE EXISTING NETWORK IS ABOUT 38241 MTR BUT SOME AREAS WERE FOUND MISSING & DAMAGED IN THE EARLIER RECORDS. IN WHICH 5546 METER NEW LINE IS PROPOSED.REPAIR APPROX 24918 METERS OF THE DAMAGED NETWORK. HOUSE CONNECTION WITH GI PIPES & TAPS ARE ALMOST MISSING,DAMAGED. HENCE, NEW GI PIPES AND TAPS NEED TO BE INSTALLED, ALONG WITH 342 NEW HOUSE CONNECTIONS & 974 REPAIR. 6 HABITATION OUT OF 14 SUFFERING FROM WATER SUPPLY DUE TO LONG DISTANCE & CANAL EXPRESSWAY & RAILWAY CROSSING, SO WE HAVE TO CONSIDERED A SEPERATE SCHEME FOR THE SAME HABITATION. WE HAVE TAKEN NEW TW,OHT,PH SOME PIPELINE & FHTC FOR THIS SCHEME MENTIONED ABOVE.