Brief Description of Works
District
Kannauj
Scheme ID
4866619
Scheme Name
GHAMAICHMAU WATER SUPPLY SCHEME
Village Covered
1
Original Scheme Year
0
Amount (Lakh)
113.65
Retrofitting Year
0
Amount (Lakh)
97.20
New T/W
0
Rebore T/W
0
New OHT
0
Repair OHT
0
Boundary Wall and Campus Devp.
Pump House (New)
0
Pump House (Repair)
0
Pipe Line (New)
0
Pipe Line (Replacement)
0
FHTC Existing
0
FHTC Repair
0
FHTC New
0
Status
Partially Functional > 70 lacs
Specific reason for increasing cost
THE SCHEME WAS CONSTRUCTED IN 2010-11 & COVERS 2 HABITATION. HOWEVER AS PER THE PARTIAL SCHEME, REGULAR WATER SUPPLY IS RUNNING ONLY IN ONE HABITATION IN WHICH ONE HABITATION IS FULLY DEAD. DURING CONSTRUCTION, A 4 KG PVC PIPE WAS USED, WHICH IS NOW 65% DAMAGED & NON FUNCTIONAL. AS PER OUR SURVEY, THE EXISTING NETWORK IS ABOUT 14380 METER, BUT SOME AREAS WERE FOUND MISSING IN THE EARLIER RECORDS. IN WHICH 4605 METER NEW LINE IS PROPOSED. HOUSE CONNECTION WITH GI PIPES & TAPS ARE ALMOST MISSING. HENCE, NEW GI PIPES AND TAPS NEED TO BE INSTALLED, ALONG WITH 56 NEW HOUSE CONNECTIONS AND REPAIR OF 170 CONNECTION. TO ENSURE PROPER WATER PRESSURE, SLUICE VALVES & AIR VALVES HAVE BEEN CONSIDERED. SINCE, THE SCHEME IS OLD, SOME REPAIR WORK IS ALSO REQUIRED FOR THE PUMP & IN OHT SEEPAGE IN CYLIND