Brief Description of Works

District Sant Ravidas Nagar
Scheme ID 5245913
Scheme Name Jagarnathpur
Village Covered 12
Original Scheme Year 2014
Amount (Lakh) 180.43
Retrofitting Year 2020
Amount (Lakh) 244.34
New T/W 0
Rebore T/W 0
New OHT 0
Repair OHT 1
Boundary Wall and Campus Devp. Boundary wall: Provision for double priming coat with putty and double coat exterior emulsion paint. Campus development: No additional campus development works are necessary. Only the provision for internal square drain, including supply of all materials, labour, and T&P etc., complete in all respects, has been made. Provision has also been kept for a water recharge mechanism within the water works campus.
Pump House (New) 0
Pump House (Repair) 1
Pipe Line (New) 7740
Pipe Line (Replacement) 3869
FHTC Existing 2150
FHTC Repair 465
FHTC New 355
Status Partially Functional > 70 lacs
Specific reason for increasing cost Under the Jaganathpur Water Supply Scheme, Block Aurai, water supply to the villages of Derawa, Misirpur Uparwar, Basupur Uparwar, Mulapur Uparwar, Dewkli, Chak Newaji, and Chandrapura, covering approximately 465 households, has been disrupted due to choked sections of the existing pipeline and damage caused during road widening works.To restore and improve the water supply, a total pipeline length of 2150 meters has been proposed, which includes:Replacement of damaged sections of the existing pipeline along the road.Provision of new connections for recently constructed houses.Replacement and rehabilitation of choked portions of the pipeline.The necessity of undertaking these additional works—namely repairing damaged pipelines, providing new household connections, and rehabilitating choked