Jal Nigam - Old Schemes O&M Summary

Jal Nigam — Old Schemes Executive Summary

LC Infra Project Limited
Total Assign District
6
Assign Districts
1. Baghpat, 2. Deoria, 3. Ghaziabad, 4. Hapur, 5. Pratapgarh, 6. Prayagraj
Total Schemes / RVs
761/1372
DPRs to be Prepared (Schemes / RVs)
761/1372
DPRs Prepared till date (Schemes / RVs)
761/1372
Pending DPRs (Schemes / RVs)
0/0
PPRBD Approved(Schemes / RVs)
761/1372

O&M EMB Details

Total Bill Details
Total Generated Bill
9364
Total Generated Bill Amt(Lakh)
3136.89
Pending Bill
397
Pending Bill Amt(Lakh)
120.30
Paid Bill
8967
Paid Bill Amt(Lakh)
3136.89

Category A Bill Details
Total Generated Bill
1585
Total Generated Bill Amt(Lakh)
588.48
Pending Bill
32
Pending Bill Amt(Lakh)
7.90
Paid Bill
1553
Paid Bill Amt(Lakh)
588.48

Category B Bill Details
Total Generated Bill
7220
Total Generated Bill Amt(Lakh)
2519.01
Pending Bill
310
Pending Bill Amt(Lakh)
110.15
Paid Bill
6910
Paid Bill Amt(Lakh)
2519.01

Category C Bill Details
Total Generated Bill
559
Total Generated Bill Amt(Lakh)
29.40
Pending Bill
55
Pending Bill Amt(Lakh)
2.25
Paid Bill
504
Paid Bill Amt(Lakh)
29.40

Costing

Average Costing of all DPRs prepared till now (Without Solar & SCADA)(Lakh)
100.35
Average Costing of all DPRs prepared till now (With Solar & SCADA)(Lakh)
150.53

Category wise Details

Category A
Total Schemes / RVs
111/181

DPRs Prepared (Schemes / RVs)
111/181

PPRBD Approved(Schemes / RVs)
111/181

Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
40.33

Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
52.44

Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
87.95

Category B
Total Schemes / RVs
533/1046

DPRs Prepared (Schemes / RVs)
533/1046

PPRBD Approved(Schemes / RVs)
533/1046

Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
83.94

Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
109.16

Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
165.31

Category C
Total Schemes / RVs
117/145

DPRs Prepared (Schemes / RVs)
117/145

PPRBD Approved(Schemes / RVs)
117/145

Average Work Costing Per Scheme (Without Contigencies&GST&Centage)
81.27

Average Costing Per Scheme (Without Solar & SCADA) (With Contigencies&GST&Centage)
105.69

Average Costing Per Scheme (With Solar & SCADA) (With Contigencies&GST&Centage)
142.56

Agreements

Details of Agreements Signed for O&M
Total Schemes / RVs
761/1372
Agreements Signed till date (Schemes / RVs)
750/1355
Pending for Agreement signing (Schemes / RVs)
11/17
Category A
Total(Schemes / RVs)
111/181
Signed(Schemes / RVs)
111/181
Pending(Schemes / RVs)
0/0
Category A
Total(Schemes / RVs)
533/1046
Signed(Schemes / RVs)
532/1045
Pending(Schemes / RVs)
1/1
Category A
Total(Schemes / RVs)
117/145
Signed(Schemes / RVs)
107/129
Pending(Schemes / RVs)
10/16

Category Wise DPR Value

Fully Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 111 181 5821.34 52.44 32.16
0 Valued 4 5 0.00 0.00 0.00
Above 0 to 10 Lakh 1 1 8.01 8.01 8.01
10 to 20 Lakh 19 27 289.10 15.22 10.71
20 to 30 Lakh 10 16 261.80 26.18 16.36
30 to 40 Lakh 6 10 215.45 35.91 21.55
40 to 50 Lakh 12 17 556.55 46.38 32.74
Above 50 Lakh 59 105 4490.43 76.11 42.77

Partialy Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 533 1046 58182.20 109.16 55.62
0 Valued 1 3 0.00 0.00 0.00
0 to 10 Lakh 3 5 12.11 4.04 2.42
10 to 20 Lakh 4 4 62.83 15.71 15.71
20 to 30 Lakh 21 26 535.58 25.50 20.60
30 to 40 Lakh 32 32 1123.79 35.12 35.12
40 to 50 Lakh 41 48 1886.08 46.00 39.29
50 to 60 Lakh 41 64 2269.79 55.36 35.47
60 to 70 Lakh 60 104 3881.59 64.69 37.32
70 to 80 Lakh 76 151 5703.04 75.04 37.77
80 to 90 Lakh 49 105 4153.33 84.76 39.56
90 to 100 Lakh 29 51 2750.66 94.85 53.93
100 to 150 Lakh 90 181 10743.35 119.37 59.36
150 to 200 Lakh 38 88 6520.56 171.59 74.10
Above 200 Lakh 48 184 18539.49 386.24 100.76

Non- Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 117 145 12365.24 105.69 85.28
0 Valued 3 6 0.00 0.00 0.00
10 to 20 Lakh 1 1 18.39 18.39 18.39
20 to 30 Lakh 1 1 29.68 29.68 29.68
30 to 40 Lakh 5 5 175.72 35.14 35.14
40 to 50 Lakh 6 6 261.62 43.60 43.60
50 to 60 Lakh 5 6 275.60 55.12 45.93
60 to 70 Lakh 4 6 256.29 64.07 42.71
70 to 80 Lakh 14 16 1050.15 75.01 65.63
80 to 90 Lakh 18 25 1545.44 85.86 61.82
90 to 100 Lakh 9 12 836.13 92.90 69.68
100 to 150 Lakh 30 35 3623.67 120.79 103.53
150 to 200 Lakh 15 17 2574.38 171.63 151.43
Above 200 Lakh 6 9 1718.17 286.36 190.91

All DPR Range
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 761 1372 76368.79 100.35 55.66
0 Valued 8 14 0.00 0.00 0.00
0 to 10 Lakh 4 6 20.12 5.03 3.35
10 to 20 Lakh 24 32 370.32 15.43 11.57
20 to 30 Lakh 32 43 827.07 25.85 19.23
30 to 40 Lakh 43 47 1514.97 35.23 32.23
40 to 50 Lakh 59 71 2704.25 45.83 38.09
50 to 60 Lakh 59 90 3263.50 55.31 36.26
60 to 70 Lakh 78 136 5033.47 64.53 37.01
70 to 80 Lakh 98 184 7343.88 74.94 39.91
80 to 90 Lakh 80 152 6804.15 85.05 44.76
90 to 100 Lakh 44 75 4160.70 94.56 55.48
100 to 150 Lakh 125 224 14973.77 119.79 66.85
150 to 200 Lakh 53 105 9094.94 171.60 86.62
Above 200 Lakh 54 193 20257.65 375.14 104.96

Fully Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 111 181 5821.35 52.44 32.16
0 Valued 4 5 0.00 0.00 0.00
Above 0 to 25 Lakh 23 32 369.82 16.08 11.56
25 to 50 Lakh 25 39 961.10 38.44 24.64
50 to 100 Lakh 54 97 3883.68 71.92 40.04
Above 100 Lakh 5 8 606.75 121.35 75.84
Partialy Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 533 1046 58182.19 109.16 55.62
0 Valued 1 3 0.00 0.00 0.00
Above 0 to 25 Lakh 17 22 309.28 18.19 14.06
25 to 50 Lakh 84 93 3311.10 39.42 35.60
50 to 100 Lakh 255 475 18758.41 73.56 39.49
Above 100 Lakh 176 453 35803.40 203.43 79.04
Non- Functional
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 117 145 12365.24 105.69 85.28
0 Valued 3 6 0.00 0.00 0.00
Above 0 to 25 Lakh 1 1 18.39 18.39 18.39
25 to 50 Lakh 12 12 467.02 38.92 38.92
50 to 100 Lakh 50 65 3963.61 79.27 60.98
Above 100 Lakh 51 61 7916.22 155.22 129.77
All DPR Range
Range No's OF Schemes No of Rv's Total Work Cost Average Work Cost (Scheme wise)(Lakh) Average Work Cost (Village wise)(Lakh)
Total 761 1372 76368.80 100.35 55.66
0 Valued 8 14 0.00 0.00 0.00
Above 0 to 25 Lakh 41 55 697.50 17.01 12.68
25 to 50 Lakh 121 144 4739.22 39.17 32.91
50 to 100 Lakh 359 637 26605.71 74.11 41.77
Above 100 Lakh 232 522 44326.37 191.06 84.92